In this article
What is checked at the initial inspection
An initial inspection is carried out when the lift has not been put into service for more than 6 months after the certificate or declaration of conformity was issued (Art. 24(1)(1) of the Ordinance on the Safe Operation and Technical Supervision of Lifts, hereafter “the Ordinance”). It consists of (Art. 25a):
- a visual check that the lift matches the technical data, instructions and declaration of conformity submitted at registration;
- a check that the lift and its safety components bear the conformity marking.
Afterwards the body issues an initial inspection report stating the checks made, the conclusion on fitness and the periodic inspection deadline (Art. 27(1)). The body stamps the inspection logbook (ревизионна книга), enters the maintenance company in it and hands it to the user for safekeeping (Art. 29(1)).
What is checked at periodic and additional inspections
At periodic inspections and at inspections after reconstruction, component replacement, an accident or at the user's request, the following are carried out (Art. 26(1)):
- a conformity check of the lift against its technical data and, after reconstruction, against the reconstruction documentation;
- tests under the points of BDS EN 81-1+AC:2003 for electric lifts or BDS EN 81-2+AC:2003 for hydraulic lifts listed in Art. 26(1)(4).
For lifts placed on the market before 2 June 2003, the Ordinance sets the conditions for some of the tests. For electric lifts some tests are made with 110% of the rated load in the car, others with an empty car or with rated load (Art. 26(2)). For hydraulic lifts one test is made at 150% of the full-load pressure, the others with an empty car or with rated load depending on the car area (Art. 26(3)).
Who attends and what must be provided
The inspection takes place in the presence of the user and of the person who maintains the lift (or installed, repaired or reconstructed it) (Art. 25(1)). The maintenance company provides qualified staff, measuring equipment, test weights and electrical power (Art. 25(2)). Also have ready:
- the inspection logbook — the user must provide it on request (Art. 29(3));
- the keys to the machine room and pulley room — they must be permanently available in the building (Art. 13a(3));
- the maintenance company's log, kept in the machine room or, if there is none, in the control cabinet (Art. 9(6)).
What you receive after the inspection
Results of periodic and additional inspections are entered in the inspection logbook as an inspection record, which states (Art. 27(2)):
- the faults, violations and non-conformities found against the Ordinance and/or the lift's technical documentation;
- a conclusion on whether the lift is fit for further safe operation and under what conditions;
- the deadline for the next periodic inspection.
The licensed body places a sticker in the car with its registration number, the inspection date and the year of the next periodic inspection (Art. 25(3)). If it finds the lift unfit for safe operation, it notifies the regional office of the Chief Directorate “Inspection for State Technical Supervision” (GD IDTN) in writing within 3 days (Art. 27(4)), and operation is stopped (Art. 30(1)(5)).
Which faults require the lift to be stopped
The Ordinance lists faults for which the maintenance company notifies the user in writing and the lift is stopped until they are fixed (Art. 10(1)). They include:
- the car moving with a landing door open, or with the car door open while carrying passengers or goods;
- malfunction of the final limit switches, overspeed governor, safety gear, stop button, landing door locking devices or safety contacts;
- ropes or traction sheave grooves worn beyond the permitted limit;
- car floor illumination below 50 lx, water in the pit or machine room, stopping accuracy outside ±50 mm (unless the manufacturer specifies otherwise);
- a non-working load control device, or a non-functioning two-way communication link to the emergency service.
Separately, the safety upgrades under Chapter Five (Art. 38–40) — load control, emergency lighting, an emergency alarm device, a toe guard under the car — had to be completed by the deadlines in § 12 of the Transitional Provisions of Council of Ministers Decree No. 62/2014, the last of which expired on 31 December 2023. When a licensed body finds a lift operating without these measures, it notifies GD IDTN immediately (§ 12(3)).
ESTIMA KM Ltd carries out lift inspections as licensed technical supervision body (licence No. 417). See technical supervision of lifts or request an inspection.
Sources
- Ordinance on the Safe Operation and Technical Supervision of Lifts — Art. 10, Art. 13a, Art. 25, Art. 25a, Art. 26, Art. 27, Art. 29, Art. 30; § 12 of the Transitional Provisions of CoM Decree No. 62/2014
This article is for information and does not replace the text of the legal act.