Design approval for lifting equipment in Bulgaria

Sites with stationary or rail-mounted cranes, trolleys, electric hoists and mobile elevating work platforms, or with construction and other personnel hoists, must be built to investment designs approved by a technical supervision body. The body approves the design or gives written reasons for refusal within 14, 21 or 28 days, depending on the number of units on site (Art. 98 of the Bulgarian Ordinance on lifting equipment).

In this article
  1. Which sites need design approval?
  2. Which parts of the design are approved?
  3. How long does design approval take?
  4. Is repair documentation approved too?
  5. What comes after approval, and what about jib cranes on construction sites?

Which sites need design approval?

Under Art. 98(1) of the Ordinance on the Safe Operation and Technical Supervision of Lifting Equipment, investment designs approved by a technical supervision body are required for sites with:

  • stationary or rail-mounted cranes, electric trolleys and electric hoists;
  • stationary or rail-mounted mobile elevating work platforms;
  • construction and other hoists for lifting people, or people and goods.

The general legal basis is Art. 35(1)(2) of the Technical Requirements for Products Act (TRPA): technical supervision bodies approve investment designs for buildings with high-risk equipment, in the part that concerns that equipment.

The user must not allow lifting equipment to be installed without an investment design, or with a design not approved under Art. 98 (Art. 55(10)).

Which parts of the design are approved?

The following parts of the technical and/or detailed design are subject to approval (Art. 98(2)):

  1. the structural part with calculations proving that the structure can carry the loads from the lifting equipment, including the runway design under Art. 27(1);
  2. the process part, showing the position of the equipment and the safe distances to other machines, buildings and installations;
  3. the electrical part, showing the power supply and earthing of the equipment;
  4. the site plan — for complex sites.

The runway design includes, among other things, calculations for the loads in service and during the static and dynamic tests, permitted slopes and tolerances, the rail type and fixing method, the minimum curve radius and the design of the end stops (Art. 27(1)).

How long does design approval take?

The technical supervision body reviews the design and approves it or refuses approval, informing the applicant in writing within a period that depends on the number of lifting units on site (Art. 98(3)):

Lifting units on siteDeadlineLegal basis
up to 214 daysArt. 98(3)(1)
3 to 521 daysArt. 98(3)(2)
more than 528 daysArt. 98(3)(3)
Repair documentation14 daysArt. 99(1)

If the design solutions comply with the Ordinance, the body signs and stamps the design. If they do not, it gives written reasons for the refusal (Art. 98(4)).

Is repair documentation approved too?

Yes. Repairs and reconstructions outside the cases in Art. 38 are carried out to technical documentation containing an explanatory note, calculations, working drawings of the replaced or repaired parts, material data, the type and extent of non-destructive testing and of the tests, and a list of the standards applied (Art. 39(1)).

The technical supervision body approves this documentation within 14 days (Art. 99(1)). For equipment manufactured before the Ordinance entered into force, the body checks compliance with the rules in force at the time of manufacture (Art. 99(2)).

No documentation is required when parts made by the equipment manufacturer, or to its documentation, are fitted; they must then come with the manufacturer's quality certificate (Art. 39(2)). The user must not allow a repair without the documentation under Art. 39(1) or if it has not been approved (Art. 55(9)).

What comes after approval, and what about jib cranes on construction sites?

After installation the user registers the equipment with a technical supervision body of its choice. The registration request includes a copy of the approved design under Art. 98(1) where one is required (Art. 101(2)(4)). The body checks the documents within 14 days (Art. 102(1)) and, after registration, carries out the initial inspection (Art. 108(1)(1)).

Jib cranes used for construction and assembly work are positioned on site according to a separate plan under Art. 5(1). It covers the cranes' capacity and outreach, safe distances to power lines, traffic routes, buildings and storage areas, layout and power-supply schemes, and safety measures. No such plan is needed for a truck- or chassis-mounted crane used to install machines weighing less than 80% of its maximum capacity for the relevant load chart (Art. 5(2)). A copy of the Art. 5(1) plan is attached at registration where required (Art. 101(2)(5)).

ESTIMA KM Ltd approves designs and repair documentation as a technical supervision body holding licence No. 485 for lifting equipment. Send your design via ESTIMA KM offices or see technical supervision of lifting equipment. For the next steps, read Crane and hoist inspections: intervals.

Need an inspection of lifting equipment?

Call or write to us.

Sofia: +359 2 951 54 53 Lifting equipment Work out the date

Sources

This article is for information and does not replace the text of the legal act.

Frequently asked questions

At what design stage is approval given?

The parts of the technical and/or detailed design are approved (Art. 98(2)).

Is a site plan required?

A site plan is approved only for complex sites (Art. 98(2)(4)).

What happens if approval is refused?

The body gives written reasons when the design solutions do not comply with the Ordinance (Art. 98(4)).

Can a crane be installed before the design is approved?

No. The user must not allow lifting equipment to be installed without an investment design or with a design not approved under Art. 98 (Art. 55(10)).