Which pressure equipment is under technical supervision?
Under Art. 2 of the Ordinance on the Design, Safe Operation and Technical Supervision of Pressure Equipment, this covers permanently installed:
- metal vessels for gases, vapours or liquids under pressure, where the pressure at maximum allowable temperature exceeds atmospheric pressure by more than 0.05 MPa and volume in litres times pressure in MPa exceeds 100;
- steam boilers above 116.3 kW thermal output;
- hot-water boilers above 116.3 kW thermal output;
- metal steam piping above 0.6 MPa where maximum allowable pressure in MPa times nominal diameter in mm exceeds 100;
- metal hot-water piping above 110 °C under the same pressure-diameter condition.
The Ordinance does not apply, for example, to equipment on vehicles, fire extinguishers, breathing-apparatus cylinders, gas appliances, radiators and piping in water heating systems (except piping under Art. 2(5) and (6)), or domestic hot-water cylinders (Art. 3).
Intervals by type of equipment
The intervals are set in Art. 265(1)(2) and (3):
| Equipment | Periodic inspection | Inspection with strength test | With an RBI plan — at least every |
|---|---|---|---|
| Pressure vessels, steam and hot-water boilers | once every 4 years | once every 8 years | 6 years (inspection) / 12 years (test) |
| Steam and hot-water piping | once every 12 months | once every 8 years | 12 years (test) |
The longer intervals under a risk-based inspection (RBI) schedule are allowed only for equipment to which EN 16991 (BDS EN 16991) applies, that has an internationally recognised risk-based inspection methodology, and where that methodology has been accepted by a certified specialist in line with internationally recognised practice (Art. 265(1)(2)(a) and (3)(a)).
For details of the test, see Strength testing of pressure equipment.
Work out the date with the inspection date calculator.
Can the inspection deadline be extended?
Yes, by no more than 6 months and only with the agreement of the technical supervision body (Art. 265(6)). The user submits a justified written request guaranteeing safe operation until the new date, together with the organisational and technical measures that will ensure it (Art. 265(7)).
When is an additional inspection required?
Besides the initial and periodic inspections, the technical supervision body carries out inspections (Art. 265(1)(4)–(9)):
- after reconstruction;
- when the equipment has not been used for more than 12 months;
- after replacing or repairing pressure-bearing parts;
- at the user's request;
- after a pressure vessel or boiler has been relocated.
Unannounced inspections are carried out by the Chief Directorate “Inspection for State Technical Supervision” (GD IDTN), for example when periodic inspections are overdue and no request has been filed (Art. 265(4)). If the equipment is scrapped or has not been used for more than 12 months, the user notifies the body within 10 days (Art. 263).
How is an inspection requested and what is checked?
The user sends a written request to the body that registered the equipment (Art. 265(2)). The inspection is carried out within 2 weeks for initial and additional inspections and after relocation, and within 6 weeks for periodic inspections and those at the user's request. The date is announced at least 5 days in advance (Art. 265(3)).
Every inspection includes an external examination (Art. 267(2)(1)). It covers conformity with the documents, records of safety-valve checks, corrosion, cracks and deformation, supports and joints, safety devices and fittings, and earthing and lightning protection (Art. 273(1)). On request the user removes some or all of the insulation.
An internal examination is done where possible (Art. 267(2)(3)). For it the user shuts down, cools, empties, blanks off and cleans the equipment (Art. 274(1)). The user may ask for the internal examination to be replaced by ultrasonic weld testing and thickness measurement concluded by an accredited inspection body, or by a remaining-life assessment (Art. 274(5)). If a vessel cannot be examined internally because of non-removable internals, linings or packing, a hydrostatic test is done instead (Art. 269(1)). Insulated cryogenic storage vessels get an external examination only (Art. 269(5)).
After the inspection the body fixes a sticker with the registration number from the DAMTN (State Agency for Metrology and Technical Surveillance) information system, the inspection date and the next due date (Art. 267(4)), and enters a report in the logbook (ревизионна книга) (Art. 277(1)). If the equipment is unfit, the licensed body must inform GD IDTN within two days (Art. 277(4)).
ESTIMA KM Ltd is a technical supervision body holding licence No. 834 for pressure equipment. Request an inspection via technical supervision of pressure equipment or ESTIMA KM offices; for what such a body does, see What is a technical supervision body.
Need an inspection of pressure equipment?
Call or write to us.
Sofia: +359 2 951 54 53 Pressure equipment Work out the dateSources
- Ordinance on the Design, Safe Operation and Technical Supervision of Pressure Equipment — Art. 2, 3, 263, 265, 267, 269, 273, 274, 277 (as amended by SG 61/2023)
This article is for information and does not replace the text of the legal act.